Hello SmartSheet community,
I would like to add bankholidays under a "depencies disabled" mode.
It this possible ?
I take it that with a "dependency enabled" mode, that's already feasible.
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Best
Hello,
At this time, dependancies must be enabled in order for non-working days or holidays to be excluded in the duration calculation.
As a workaround, you could create a formula using the NETWORKDAY function to calculate the number of days between two dates, adding 1 day to the result if the start date is a non-working day.
The NETWORKDAY function allows you to enter the dates you would like to exclude. More information on this function can be found here: https://help.smartsheet.com/function/networkday
I submitted a ticket, but thought I would ask here. I am having an issue with sheets that I own (our org is on a Business plan). For the last two years, we have been using the sheets without an issue - our admin and many Editors (all shown as Guest since they are outside of our organization) were able to edit the sheets…
Hello! I’ve noticed for a LONG time that when I change the name of a column in a source sheet, the corresponding column in reports breaks, which then causes dashboard widget charts (that rely on those reports) to fail. Is there a way to: Prevent this issue when renaming columns? Fix existing reports and dashboards without…
Dear All, my account was suspended for a long period in which my sheets were deleted. I renewed my account and asked technical support if my sheets could be recovered. I received this message below, but I do not seem to get a reply back afterwards and still do not have my sheets recovered. Thanks for…