Row Level reminders (over allocation)

Does anybody have experience with a report showing over allocated persons in a project?

What I mean is when person A works in project X on day 1,2,3 and 4. And the same person A is working in project Y on day 2 and 4.

In this situation person A is over allocated on two days: day 2 and 4.

How to get this nicely reported in a report across differend projects (and persons).  