Postpone the start date of a project

Neeraj
Neeraj
edited 12/09/19 in Smartsheet Basics

Hello Community members,

 

I want to extend the start date of my project schedule(Gantt chart) by 2 weeks. I have no dependencies and I just want to statically push the dates for all tasks by 2 weeks. Can this be done in smartsheets.

 

Appreciate your help.

Neeraj

Comments

  • Gunn_Jack
    Gunn_Jack ✭✭✭✭

    Hi Neeraj,

    In my experience without the dependencies you would have to do this manually (i could be wrong though if anyone knows a way to do this).

    What I would do is create a date column next to your current one and formula it to add 14 to your current dates. Simply then copy and paste your new dates into your original date column. Ensure you select 'Paste Special' and then 'Values' so your formula does not carry across.

    As above, this is the only way I can think to do it quickly unless anyone else knows another simpler way?

    Thanks,

    Jack