Sign in to join the conversation:
I have a project where the planned tasks are spread over several weeks, see attached.
How is the summary % complete total calculated? Can I relate to %complete against project days?
Regards
Steve
The summary % Complete is an average of the children.
Can you explain in more detail what you mean by "Can I relate to %complete against project days"?
Hi Paul,
Thanks for your reply. From my example 44% complete implies 1.10 days completed in the project. However, project days x %complete gives 1.15. Is this correct? Because my project days are spread over a longer durations, what the best way to represent the %complete?
Regards Steve
That depends on the level of accuracy you are looking for. the 0.05 days difference relates to 1 hour and 12 minutes difference.
Also... What is the difference between the Project Days and the Duration?
I'm just struggling to figure out exactly how your process is working.
Project days are the days sold to the client for the delivery of a task. However, this may be spread over weeks which gives a longer duration in smartsheet, e.g. 18/08/19 to 28/08/19 gives 9d duration but the time spend on the project is 1 day spread over the 9d.
So could it also be said that the duration is 1 day with 8 days lag or lead time?
Hi Paul, that's correct. However, the nature of our construction projects is that 1 day is schedule over 2 weeks but we not sure when the work would actually be done so the plan shows the duration as 10 days against 1 project day. Regards Steve
You would need to be able to build in actual start and finish dates and run your % Complete off of those then.
Hi Paul, OK, thank you, regards Steve
Happy to help!
@Paul Newcome , Hope you are well. Question for you, meant to ask quite some time ago but forgot. You had shared this right after Engage 2025. I'm unfamiliar with the view and how to create it. Can you tell me about this view?
I am trying to change owner on a Smartsheet sheet to the owner of the workspace it is located in. I keep getting an error message stating the permissions need to be managed at the workspace level. I am unable to change owner for the sheet at the workspace level. Not sure how to accomplish this change. HELP!
I would like to add two dynamic filters as a widget within my Dashboard to define a date range (start and end date) which would then return a count value to that same Dashboard. I have been searching for answers but am not coming up with the solution I'm looking for. What is the cleanest way to configure this?