Welcome to the Smartsheet Forum Archives


The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.

Start and Stop Tasks / Breaks in Progress

Chris Keck
edited 12/09/19 in Archived 2016 Posts

     I want to be able to reflect task start and stop dates within a project management sheet. For example, A task begins on Monday and work is done until Wednesday, but on Thursday work stops because of some unforeseen circumstance and the task is resumed and completed on Friday. As it stands I can show in a single row that it had a start date of Monday and finish date of Friday (duration of 5 days). 

     But what I want to show on my sheet is that there was no work done on Thursday, and the actual # of days of work to complete the task was only 4. How can I input a break of progress and have it reflected in a single row of Gantt? 

 

Comments

This discussion has been closed.