Task A
Task B is dependent on Task A
Task C is dependent on Task B
For some reason, I was able to finish Task B and Task A was getting delayed. How do I:
1. Extend duration of Task A without impacting dates, duration or status of Task B?
2. Mark Task B complete, such that actual completion dates do not change irrespective of any changes to Task A
3. Drive changes to Task C based on the fact that Task A is still incomplete
In P6, there is an "actualize" option that marks dates as actual and would transfer dependencies of that completed task to the incomplete predecessor task. Is there a similar functionality in smartsheets?