How to "actualize" or transfer dependencies of a completed task?
Task A
Task B is dependent on Task A
Task C is dependent on Task B
For some reason, I was able to finish Task B and Task A was getting delayed. How do I:
1. Extend duration of Task A without impacting dates, duration or status of Task B?
2. Mark Task B complete, such that actual completion dates do not change irrespective of any changes to Task A
3. Drive changes to Task C based on the fact that Task A is still incomplete
In P6, there is an "actualize" option that marks dates as actual and would transfer dependencies of that completed task to the incomplete predecessor task. Is there a similar functionality in smartsheets?
Comments
-
Hi,
Seems like your dependencies are not working as they should.
If task B is dependent on Task A, how were you able to finish B with A being delayed?
Do you have dependencies active?
Also screenshots of your spreadsheet would be useful.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!