One Dependency for the start, another for the end?
Hi... I'm trying to set up a project that has a task (weekly update reports) that begins with one dependency (e.g., start of project), and ends with another dependency (e.g., on-site work). There are still some administrative tasks that continue after the on-site work is done, but I won't have to continue the update reports for them.
I've tried to set up a SS dependency on the top Predecessor line, and a FF dependency on another Predecessor line, thinking that it would tie my duration to both the Start of the project and the Finish of the on-site work. But that doesn't seem to do the trick.
I've also tried to use a cell-to-cell reference for End Date in the End Date cell of weekly update reports (=[End Date]9) but that doesn't even calculate. Probably trying to use Excel reasoning, lol...
Any thoughts?
Thank you very much for any help!!
Ron
Answers
-
The formula for the cell reference won't work because formulas in general do not work in columns being used by the dependencies.
Have you tried other combinations for the predecessors such as SF and FS?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 462 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives