Story points/sprints mapped to duration for use in gannt chart
I am really struggling to make this work in my project.
I have a calculation formula which turns the sprint estimates into a number.
E.g 1 = 14, 2 =28, 3 = 42 etc
I am trying to get the duration column to pick this up nd hence give me the value in days which then correctly moves the gaunt chart if a start date is entered. I can't seem to make it work. Does anyone have an answer of how to do this?
Answers
-
I would set up the formula in the end date such as =[Start date]@row + (formula that turns sprint estimates into a number)).
Josh
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives