Maybe the wrong software?
Comments
-
Hi Tim—A couple of points of note on this:
1. Although the browser app Gantt chart timeline is down to the day, you can record partial day duration in hours using the Duration column on your sheet. (You likely already know this.)
2. You can currently see the Gantt duration in 2 hour blocks in the iOS and Android apps.
I've added your vote to our enhancement request list for a method to get the Gantt timeline down to hours in the desktop browser application.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives