Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Gantt Chart sum of days for subtasks
Hello everyone,
We're using gantt charts to planify our tasks. When creating task groups and sub-tasks, the number of days displayed in the task group does not reflect the actual number of days planned but the time span from the beginning of the first task to the end of the last task. This creates confusion when presenting the chart to our customers.
Example:
Group Interal Tasks 102 days Start 19/09/16 End 07/02/17 12%
--> Sub Task Migration 4h 19/09/16 19/09/16 100%
--> Sub Task Documentation 2d 05/12/16 06/12/16 0%
--> Sub Task Server setup 1d 07/02/17 07/02/17 0%
As you can see, the tasks are wide spread on the timeline and instead of counting a total of 3.5 days it shows 102 days (from beginning to end).
Is there any way to show the sum of the actual days?
Thanks for your help,
Stefan
Comments
-
1. Create a specific column, called for instance "Active days"
2. At your 'Sub task' level, type he formula
=Durationx
. Considering that your Duration column is called 'Duration'
. x is the same row number (therefore on row #40, the formula will become =Duration40)
→ You will see that the result is smartly converting hours in fractions of days.
3. For higher levels, in the new column type the formula
=SUM(CHILDREN())
→ Check it does answer your need.
4. Hide the 'Duration' column and show the 'Active days' column to your customers.
You may actually display this new calculated figure on your Gantt chart :
a. Display Gantt, Go to the clog (top left of the Gantt)
b. Go to 'Timeline display', then 'Display label for' and select the 'Active days' column.
-
Great! Thanks
-
You can even go further by multiplying the time by the % achieved (in another column?)
Good luck
-
I've been looking for a method for this, having failed I stopped using hierarchy in sheets for similar planning. This solution looks great, I'll try it. Thanks
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives