Instead of an even roll-up - can the parent percentage be set to a specific value relative to the project - see my example below;
1. (Project) Big Steel Project - 100%
2. (Parant)Steel Box - 50%
3. (Child) Bottom 70%
4. (Child) Sides 30%
5. (Parant)Steel Post - 30%
6. (Child)Short Posts 20%
7. (Child)Long Posts 80%
8. (Parant)Steel Beams - 20%
9. (Child)Short Beams 50%
10. (Child)Long Beams 50%
The problem I'm having is that the completed percentage is not reflective of actual workload to be completed.
Thanks for your help