How can I compare two date columns in an automated workflow?
Answers
-
if(sdate@row <> edate@row,1,0)
goes in a helper column
Then run the workflow on the helper column instead of the date columns.
-
Thanks so much! I was finally able to do it
if(sdate@row <> edate@row,1,0)
goes in a helper column
Then run the workflow on the helper column instead of the date columns.