Percent Rollup Working Inconsistently
We are tracking Open Enrollment for several clients in two major categories - MED and FLEX - with tasks necessary for each. In the screenshot, the percentage for the client at the top is rolling up, but the the bottom is not.
Is this because the first item has a duration of ZERO? I would still think marking it as 100% would have some impact on the overall percent, but it doesn't cause any change.
Best Answer
-
I know I just posted this, but that is what is happening. If I change duration from ZERO to even just 1H, I can see the impact. I was just trying to register this task as a point in time - when we're scheduled to receive enrollment, however, I may want to reconsider this approach. Thanks for reading and maybe this will help some other person if they read it. 😀
Answers
-
I know I just posted this, but that is what is happening. If I change duration from ZERO to even just 1H, I can see the impact. I was just trying to register this task as a point in time - when we're scheduled to receive enrollment, however, I may want to reconsider this approach. Thanks for reading and maybe this will help some other person if they read it. 😀
-
Thanks for posting what you found out, @Marvin Daniels!
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 35 Webinars
- 7.3K Forum Archives