Hi
I am trying to create a Project Schedule with Budget and Variance and include an overall status using the status of the child rows.
I have 1 line that is the overall project and then 4 phase lines, with around 20 tasks underneath each phase line. I want the phase lines to give an overall status of the child task rows and then the overall project line to give an overall status of the whole project based on what is on the all of the lines.
I want it to work on the same principle that the RYG balls work
I have
In progress
Completed
Not started
For instance if 3/4 of the status' are in progress then the parent line should state in progress. So basically if the average of the whole phase is in progress then the parent line (phase line) should state in progress and the same for the overall project line
Thanks in advance