Project tracking Gantt
Hey all, new to the Smartsheet community. I currently have a form that our users enter a request for and all the info is dumped into a sheet. Works as designed.
What I know need to figure out, after 70 rows of info, is how I can treat or track each row as a separate project, which they are. I'd also like to have a dashboard, or someplace that I can track all of my project statuses and milestones.
Any help would be great. I've thought through a lot of this, just not sure how to implement it.
Thanks in advance!
Best Answer
-
Yes, but you'd need to recreate the form in the new sheet/solution or modify the current one and connect it to the new structure.
The Project Intake Template Set would be a great starting point.
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Answers
-
Hi @CameronKeel
I hope you're well and safe!
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
I hope that helps!
Be safe and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I guess my workflow is a little all over the place. Associates will fill out a form, requesting a new conference room buildout. They enter all the information, site, location, size of room, use of room. I then take that info drop it into a Google Sheet, we are a GSuite shop, one for each room. That sheet is attached.
So at this point my Smartsheet is 70 rows of individual room information, with no true tracking other than a status column with a drop down that I change manually. No type of tracking, or true project management. Yesterday I laid out all the tasks associated with a room buildout, and for us it's about 20 tasks. That times 70 rooms is daunting.
Thanks for looking at this.
-
I'd recommend creating a so-called Intake Process where all projects are added and then a Template Project Sheet connected to the Intake sheet.
You could then add an ID in the Template Project sheet, which would populate the information from the Intake sheet.
To view it all together, you could either use a report or link back the information from each project to the Intake sheet.
If you'd like to automate almost everything, you could use the Premium App, Control Center. Is that an option?
Make sense?
Would that work/help?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
That's exactly how I had it in my head. Is it possible to take my current form and connect it to a template project sheet as you mentioned?
I just looked at the Project Intake template set that is in the solution center.
-
Yes, but you'd need to recreate the form in the new sheet/solution or modify the current one and connect it to the new structure.
The Project Intake Template Set would be a great starting point.
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Thank you so much for the info and quick response!!
-
You're more than welcome!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives