End Date Formula Work-Around when Dependencies are Enabled
Kelly Pratt
✭✭✭✭✭
Hello!
I am working in a sheet where I need dependencies enabled because we are using the GANTT view to show in a report on a dashboard, however I also need the end date of that sheet to be calculated (it is calculated based on another date in the same row).
When dependencies are enabled, I'm not able to put a calculation (ie formula) into the end date column. Are there any workaround solutions for this?
Appreciate your input!
Tags:
Answers
-
If you are not using predecessors, you do not need dependencies turned on to show data on the Gantt view.