Hello!
I am working in a sheet where I need dependencies enabled because we are using the GANTT view to show in a report on a dashboard, however I also need the end date of that sheet to be calculated (it is calculated based on another date in the same row).
When dependencies are enabled, I'm not able to put a calculation (ie formula) into the end date column. Are there any workaround solutions for this?
Appreciate your input!
Tags:
Answers
-
If you are not using predecessors, you do not need dependencies turned on to show data on the Gantt view.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.5K Get Help
- 367 Global Discussions
- 202 Industry Talk
- 432 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 285 Events
- 36 Webinars
- 7.3K Forum Archives