Integrating Resource Management with Control Center requires the use of an Intake Sheet with populated Start / End Dates. These fields flow into the Project-level setting in Resource Management.
However, when the schedule template (e.g. project plan) is connected these overall dates do not get updated in Resource Management to reflect the actual start / end dates in that template. Instead, I have to create a net new project.
Is this expected behavior? If so, the Control Center automation doesn't make sense with RM integration turned on.