Is Smartsheet experiencing issues with dependencies functionality?
I am currently experiencing issues with dependency functionality. This seems to have started 11/3/22. The functions FS and FF are not working. When FS and FF are leveraged, they extend the dates duration to 2 days vs the 1day duration preset. Are other users experiencing similar issues? Is there an expected resolution on this, if so?
I have been working in Smartsheet using dependencies for over a year now, and never ran into this issue until 11/3.
Answers
-
I hope you're well and safe!
Yes, I've seen multiple similar reports, and Smartsheet is investigating.
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Andree,
Thank you for the speedy reply! Noted this is an issue that others have also reported and Smartsheet is looking into resolution.
Do you have any sense of ETA for resolution? Are other users only impacted with SF and FF dependencies not working?
Any additional insight you have would be helpful!
Thank you!
Nancy
-
Happy to help!
Here are some others with similar issues.
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up/Awesome or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
So glad to see I'm not the only one with this problem and that Smartsheet is fixing it. Although I ended up adjusting my schedules and now after they fix it I'll have to change them again. :-/
-
It's been over a week since the issue started and we still don't have a resolution from Smartsheet. However, have been informed by Smartsheet support that the engineering team is working on it, as a priority. There is no estimated timeline for this fix as of today.
-
Good afternoon,
Today I have the same problem; I have not been able to work my schedules because the predecessors do not work correctly; any change that I need to make seems to be an error window; I issued a ticket with the problem, but I have not received a response yet, this has delayed everything my work today...
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.1K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 450 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 289 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!