Control Center: Linking an intake sheet field to metadata for existing projects
Hi,
Using control Center, I am looking for a way to change project managers for existing projects. Once the project is provisioned the project manager is set at that moment in time. I have fixed this problem in the blueprint to link to the intake sheet. now if I change the project manager on the intake it changes the project manager on the metadata.
This works great but I have not been successful getting Global Update to create that link on previously provisioned projects. So going forward I can change the project manager on new projects but not on existing.
Any ideas?
Answers
-
That's going to be a rather manual process.
I personally try to leave the intake sheet alone as much as I possibly can so that we have the historic record. If I want to change metadata, I will create a report that pulls in all of the metadata sheets and have it filtered to only show those fields I want to be able to change.
-
At the highest level what I am trying to do is have a function that will allow me to switch project manager to someone else. Project Manager is profile data in the metadata on the project
-
Right. So if you wanted it linked to the intake sheet to be able to change it there, you would need to manually link all existing projects.
I personally would not link it to the intake sheet. I would create a report that pulls in all of the projects' metadata sheets, have it filtered to only show that one row from each sheet and then change it there in the report.