-
Manpower Loading Schedule
I am trying to create a Project(schedule) that has a manpower loading functions. I am almost there but I am stuck with trying to figure out how to see how many crew members I have on a certain days by suming them up. For example I would like to have a list of dates and then show how many crew members working on those…
-
Is there anyone on the millwork shop side that can collaborate with me on how they use Smartsheet'?
We are a millwork shop that uses Smartsheet for all of our projects. I want to see best practices on how to use Smartsheets to our advantage. As of right now we have a "sheet" that works as our production schedule but it just seems like a big sheet with lots of data. Thanks in advance.
-
Form Options - Automation
Good morning, I'm trying to create a form in for entering and/or removing equipment from our site. There are times we have new equipment installed where equipment is not removed, and vice versa, but also times where both apply. Essentially, our wish is that the contractor would complete the form and if they check a box…
-
JOIN DISTINCT COLLECT or JOIN INDEX COLLECT w/ Multi Dropdown List
Hi, I want to return the "Assigned to" contact for the "Assignee Role(s)" selected in a multi-select dropdown list. Here are the formulas I've tried so far: JOIN(DISTINCT(COLLECT({Project Settings - Team Members}, {Project Settings - Contact Role}, CONTAINS([Assignee Role]@row, @cell))), ", ")) JOIN(INDEX(COLLECT({Project…
-
Sum Collect - not working on new blueprint sheets
I am trying to reference a source sheet on project specific sheets rolled up from a control center blue print. I am using Sum Collect to gather the sum of transactions based on Project number, cost code and category. The Sum Collect formula is working on some sheets, but not others. =IF(Summary@row = 1, "", IF(Children@row…
-
Looking for a cell value to trigger a formula
I'm looking for a formula to reference the value in a column then run a formula. I am using this to check the status of a contract then run a formula to see if too much time has passed in that status. If contract status is "In Legal" look at date sent to legal and make the value expired if seven days have past.…
-
Looking for a labor capacity tracking solution - SS Resource options won't work
Hello, I've seen a few people asking questions that lead me to believe I am not the only person looking for a labor tracking solution NOT at the day level. To use the resource tools in SS we would need people to estimate their workload on a daily basis with start and end dates. We want people estimating hours per week per…
-
Extract Cell History For Formulas
Hello, Is there any way to extract the Cell history to calculate formulas. What I am trying to do is create metrics off the dates in the cell history. I.E. if a Dropdown list column starts on July 1 with Value 1 and changes to Value 2 on December 10th then Value 3 on December 21st. I want to measure and tract the time…
-
Show ONLY Tasks in a Date Range
Is there any formula and/or filter that will enable me to show only the tasks that are scheduled to happen during a particular 3 week time frame, much like a 3 week lookahead. I want to show tasks that, during the time frame, have the following criteria. Begin and End AND is INCOMPLETE OR Begin AND is INCOMPLETE OR End AND…
-
Add "active" email addresses into Dashboard
I have a list of project team members on the Dashboard. Is there a way to show email address that will create an email when "clicked on"?