How can I view the Gantt chart in days?
When I use the zoom-in option, I can only see the day names but not the specific day numbers. I need my team to be able to see the exact dates for the tasks I have scheduled.
-
Displaying multiple time periods in Gantt view
Is there a way to display multiple time periods in Gantt view? Example: you have staff members that are your primary people, and they are contracted for 4 months, and then secondary or "fill" staff members that sit in when the primary is away on sabbatical or similar break. Idea here is that the gantt bar on a given row…
-
Incremental Baselines & Dynamic Baseline Linking
Problem: Current Limitations Destructive Updates: Currently, snapping a baseline is a global action for the entire sheet. There is no way to baseline newly added scope (new tasks) without overwriting and erasing the historical variance data of the existing tasks. Manual Data Entry: Users are forced to manually copy/paste…
-
The "Master Program View" (Dynamic Sheet Aggregation)
Problem: Current Limitations Reports are "Flat" Lists: Current Reports can aggregate rows from multiple sheets, but they function as static lists. They cannot perform project logic (dependencies, duration calculations) across those sheets. No Cross-Sheet Critical Path: There is no native way to identify a "Critical Path"…
-
Time slots on calander?
We have a machine we want our coworkers to start requesting, daily and hourly. So if Joe wants to use the machine, he could go to the calendar and see an empty time slot between 1pm-2pm and he would be able to block that time out. Does smartsheet have anything like that? Kind of like an outlook calendar
-
Modified SUCCESSORS() function to report more than just direct successors
WHY IS THIS USEFUL? This updated function would allow us to filter the spreadsheet for only the driving path to a particular row#. This would be similar to a filter for critical path, but enable much more flexibility. Current status: I've successfully generated a "Successors" column, listing direct successors of each row,…
-
Allow Gantt view to use Date columns with Column Formulas for Start/End
I'm kind of flabbergasted that this is not currently possible in a Sheet, and I'm struggling to explain to my users why. It is already possible to populate a Date column with a Column Formula and then convert it to a Cell Formula, and then use that column as the Start/End for Gantt view / Project Settings, so the issue is…
-
Time Tracking
I'm new to SmartsSheet and don't see an obvious way to track time, and have it recorded against a task Personally not too fond of % complete - to often I've seen people say/think (legit or not) that they're 90% done, and the last 10% takes as long as the first 90% (or, unfortunately, more) People often think they're almost…
-
Merged: Add elapsed days in predecessor column
This discussion has been merged.
-
Merged: Gantt hour-by-hour
This discussion has been merged.