-
Is there a way to hide a completed row (% Completion Column) in a project?
Using a project smart sheet with Gantt functionality, I would like to be able to hide competed tasks in the project sheet. It is used for production scheduling so the once a task is completed it is not needed to be viewed again unless desired. Note... predecessors are used so deletion of the task is not desirable.
-
See summarized duration/ % for header tasks
I have created a master sheet that links all my project gantt charts. Unfortunately I cannot see the summerized totals - is this available as an automatic function? I've been manually typing it in, but I'll have a lot of projects so this would be great if it was automated!
-
Trailing Commas Break Predecessor Logic
Before the new Predecessor column type was created in the Critical Path update, Smartsheet would automatically truncate extra commas or spaces in the Predecessor column. Smartsheet no longer does this, and it not only "looks" bad, but if the column isn't cleaned of these extra characters, the Predecessor functionality for…
-
planned versus actual
Is there a way to track what hours are actually spent on a task in relation to the hours that were planned?
-
what is the best way to Integrate smartsheet into an Order based Manufacturing company ?
So i have been tasked with learning the In's and Out's of smartsheet and to find the best way to utilize all of its tools for our company. we currently do the majority of our work through GP which as an accounting program is great but doesnt have the best project managment capabilities. my Question is what would be the…
-
Work Hour Based Resource Planning
Hi; I'm working on resource planning for our projects right now and wonder if there is a way of planning based on working hours or based on periods of 1/4 days (not only based on work days)? Or if not; do you have plans for implementing such functionality?
-
Date/time and year
Im trying to put together a simple Gannt chart for a project in the UK. How can i make a change to the date so it reads day first, then month, then year?
-
Gantt Chart Dependency Settings - Choosing new date range display columns deletes the formulas in th
Hi; When I choose columns (which includes formulas) for the "Start date column" and "End date column" in the "Edit Gantt Settings->Dependency Settings" dialog, formulas in the cells of newly selected columns ("Date range display" options) are being deleted automatically. Is there a way to prevent this? Note: I need to swap…
-
Gantt Chart Navigation
When I set the timeline of Gantt Charts to "Primary heading: Weeks" and "Secondary heading: Days" I cannot past the last process step while scrolling on the X Axis. Is there a way to do that? A little bit more freedom on the X axis navigation would be welcome.
-
Text not moving over when I indent
When I indent a row to show a parent / child relationship, the child is not indenting visually. I can't find any configuration to help. Any ideas?