-
Dependencies - use percentages
Add the ability to use percentages in dependencies or formulas
-
Printing Gantt/Exporting to PDF Not Working
I've been trying to print my gantt chart and all that happens is a new window will pop up in my browser and never load anything. I'm not sure what to do -- it's a brand new sheet with not a lot of data on it, I've changed the print settings multiple times, I've adjusted the gantt view. The only thing that has worked was…
-
Highlight GANTT columns
Hello all, I do have a GANT I'm using to plan some Project activities and we do deploy in PROD just once in a month. Is there a way to highlight the columns of a precise week (2nd or 4th) with a different color or something similar to make them stand out?
-
Week Numbers
Hi, I can't be the first to have asked this, but I have not found anything on the forums or community- I really want to be able to add week numbers to the top lines of a gantt. This would be very helpful, particularly when working with remote teams who work in countries/ areas that do not follow a western standard week. In…
-
Gantt Chart with multiple dates in one line?
Hello SmartSheet community! I'd like to double check with you if Smartsheets gantt charts has the posibility of displaying multiple dates in one row, I know there's been several posts regarding this topic, but I was hoping maybe the tool has been updated? If not, is there's an easy work around to display in a Gantt chart…
-
Hide non-working days in GANTT Views
I would be good to have an option to NOT display the non-working days when in GANTT view in a Sheet or Report. By displaying the weekends and holidays, This could be achieved by changing the Project Settings, in either Timeline Display or Dependency Settings (under edit Non-working days) as a checkbox. Without this option,…
-
Highlight conflicting predecessor relationships
It is possible to create predecessor relationships that are not possible. Consider: Task C is supposed to finish at the same time as Task A, but it can't because of other constraints. Currently, SmartSheet silently ignores a condition like this. This happens to me when trying to build a project around external constraints…
-
Pipedrive + Smartsheets
When a deal in my pipedrive reaches a new stage 'Job Scheduled' it automatically adds a new row to Smart Sheets with a Task Name and Duration. What I need Smartsheets to do next is automatically enter a starting and end date based off of the row above Predecessors and autofill a new Predecessors for the next row that will…
-
Is there a way to have data from one sheet auto update the start & finish date within a schedule?
I have built a schedule with proposed start/ finish dates (which are driving the Gantt) as well as a column for the actual start/ finish dates. I can link the actual columns to the data sheet where teammates are inputting their actuals, but those columns do not drive the Gantt chart to show if any lag has occurred. I am…
-
Representing Milestones landing in Financial quarters
Hi, I'm new to Smartsheet and hoping that what i'm trying to achieve may be possible but have drawn a blank on the help and community topics so far. I need to be able to represent that a project milestone is landing in a specific financial quarter and then have this represented on the Gannt chart. Ideally i would have…