-
Time Tracking
I'm new to SmartsSheet and don't see an obvious way to track time, and have it recorded against a task Personally not too fond of % complete - to often I've seen people say/think (legit or not) that they're 90% done, and the last 10% takes as long as the first 90% (or, unfortunately, more) People often think they're almost…
-
Is there a formula/function to help count number of children assigned to specific parent tasks?
Hi all, I'm trying to put together a table that lists the number of sub-tasks (children) in each respective Workstream (parent) of a specific Project Plan, and also breaks these down into their respective Health Status (Green, Yellow, Red). I am aware that I can apply a "COUNTIF" formula and set the range to encompass the…
-
Start and end date line chart
Hi Team, Can anyone help me how can I create a line chart based on below information. I
-
Dependency Logic based on one or the other predecessor tasks
Is is possible to create schedule logic where a dependent task is dependent on one of two predecessors (either or not both)? For Example: I am trying to build out a schedule template for if a permit is required vs not for a specific project. IF a permit is required then the rest of the schedule should be based on the…
-
Gnatt chart Bar formatting - grid missing
H Folks, For some reason I have areas in my smartsheet plan that have grid missing, some are ok. Does anyone have an idea how I can correct this and add the gridelines back please. thanks Mark,
-
2 or more projects sheet dependency
HI, I am using Smartsheet and I am involve in 3 projects and all are main and lead roles. I made 3 separate sheets for each project but I realize each projects affect the other projects and then sometimes the predecessor is in another sheet. >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> For example: Project A sheet Task # 25 on…
-
Data storage EU
Hello! I'm afraid my question is not a new one, but I'm not giving up hope that Smartsheet is interested in expanding into Europe. Since I realized, that EU-GDPR seems to be accepted, the IT-data-security-departments at my Clients in Germany are still focused on where Smartsheet stores the data. Tha is top level of…
-
How to create a master schedule sheet in project prog schedule mode by linking other schedule sheets
Hello, first of all sorry for my English, I'm doing a translation from French. I work in the construction industry and we have big construction projects. Each major construction project includes several complex tasks. Each of these tasks is a project in itself and it has its own schedule. The goal is to bring together all…
-
% Complete staying 0
Good Afternoon, I am new to Smartsheet, and am having trouble with what seems to be a simple task. The parent % complete will not change from 0%, no matter what I put in the child's information. Thanks.
-
Report Gantt Chart Project Settings
I am trying to change the Gantt Chart Timeline Display in a report. The report currently has the standard display as follows: I am trying to get it to look like how I have it in the original sheet below: Whenever I try and click on project settings either nothing happens or I get the error message below: I submitted a help…