Hi, I'm new to Smartsheet and hoping that what i'm trying to achieve may be possible but have drawn a blank on the help and community topics so far. I need to be able to represent that a project miles…
When a sheet is showing the Gantt Chart and you open the Sheet Summary, the left side of the Gantt Chart is pushed left to make room for the Sheet Summary. When you close the Sheet Summary the left si…
I set conditional formatting to change the task bars for each of my categories to the color that is represented in the Grid view. However, only the child rows are showing the bar color and not the par…
I am looking to develop a Gantt view that shows multiple colors on a single bar, based on the calendar, and corresponding stage of the project at that time. For example: Project XYZ, single timeline: …
Hello, I looked at several tool to manage our maintenance program. We have several equipments with subcategory that I can organize with Parent and children relationship. I have a due date and a freque…
I want to use smartsheet as an international project management tool. One thing is driving me creasy. I want to send out a notification to an assignee if the predecessor task is completed. Please find…
I'm working for a design and construct fit out company and we're looking to invest in control center and I'm just looking at the configuration of the project workspaces and need some ideas for the fol…
Hi there, Working to update a plan today and I noticed that the use of the FF Predecessor Type will cause some weirdness with the start date. I've put an example in the graphic above but the summary i…
I have a sheet that used to be operationnal, and sudenly, I get "#BLOCKED" on some of my formula. I know that the formula should be ok because I have the exact same formula in similar pages. In fact, …
Is there a way to include a milestone marker on the Gantt bar? In the example below, we would like to show the go-live date as a milestone along the Gantt bar of the execution phase.