-
Column Highlight
is there the ability to colour in a column not a row to show for example UK bank holidays or staff holidays etc.. to show in a very quick visual way any clashes that might be avoided.
-
Viewing cards from multiple different projects, all on one board
We use a separate gantt timeline for every project. We also use a simple grid to capture to-do tasks not relating to any specific project. We want to be able to view all cards from all projects, on one kanban board, to get an overarching view of everything going on. Can someone please tell me a simple way to do this?…
-
Gantt Chart Parent Row Bars
Has there been an update to allow color edit to the gantt chart parent row bars? Thanks - Julie
-
Floating dependency start dates
I have two dates: A and B. B's start is dependent on A's completion. If everything goes as planned, A will finish on 2/27 and B will start on 4/1. B's start date is constant unless A's finish is delayed beyond the planned start. For example, if A is delayed until 3/15, B will still start on 4/1; but if A is delayed until…
-
Complex Formula Help Needed
On a Gantt chart, I've added a column % Progress Expected and I have it calculating % progress expected per day for each line item, based on the duration; see formula below. =(TODAY() - Start@row) * ([ADMIN: % EXPECTED DAILY PROGRESS]@row) * 1.1 The problem I'm trying to solve for is I need it to show 0% progress expected…
-
Complex nested IF, AND with traffic light symbols
Hi All, I'm working on automating a symbol highlighter to indicate project progress as well as alerting if key milestones are being compromised. The formula below is structured based on the following columns: * Finish: The Activity completion date * Start: The activity start date * Date: A column containing fixed dates to…
-
I need to use an IF / THEN formula to compare a cell from one column to a cell in another column
I could really use some help! Thank you in advance! My STATUS column has the following colored options available per cell: Red, Yellow, Green and Blue. I am looking to use the following IF / THEN statements: 1. In STATUS, if the DELIVERY DATE is within SEVEN (7) DAYS of the START DATE, the LIGHT is RED. Can the DELIVERY…
-
Time Tracking
I'm new to SmartsSheet and don't see an obvious way to track time, and have it recorded against a task Personally not too fond of % complete - to often I've seen people say/think (legit or not) that they're 90% done, and the last 10% takes as long as the first 90% (or, unfortunately, more) People often think they're almost…
-
Is there a formula/function to help count number of children assigned to specific parent tasks?
Hi all, I'm trying to put together a table that lists the number of sub-tasks (children) in each respective Workstream (parent) of a specific Project Plan, and also breaks these down into their respective Health Status (Green, Yellow, Red). I am aware that I can apply a "COUNTIF" formula and set the range to encompass the…
-
Start and end date line chart
Hi Team, Can anyone help me how can I create a line chart based on below information. I