-
Dependency Logic based on one or the other predecessor tasks
Is is possible to create schedule logic where a dependent task is dependent on one of two predecessors (either or not both)? For Example: I am trying to build out a schedule template for if a permit is required vs not for a specific project. IF a permit is required then the rest of the schedule should be based on the…
-
Gnatt chart Bar formatting - grid missing
H Folks, For some reason I have areas in my smartsheet plan that have grid missing, some are ok. Does anyone have an idea how I can correct this and add the gridelines back please. thanks Mark,
-
2 or more projects sheet dependency
HI, I am using Smartsheet and I am involve in 3 projects and all are main and lead roles. I made 3 separate sheets for each project but I realize each projects affect the other projects and then sometimes the predecessor is in another sheet. >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> For example: Project A sheet Task # 25 on…
-
Data storage EU
Hello! I'm afraid my question is not a new one, but I'm not giving up hope that Smartsheet is interested in expanding into Europe. Since I realized, that EU-GDPR seems to be accepted, the IT-data-security-departments at my Clients in Germany are still focused on where Smartsheet stores the data. Tha is top level of…
-
How to create a master schedule sheet in project prog schedule mode by linking other schedule sheets
Hello, first of all sorry for my English, I'm doing a translation from French. I work in the construction industry and we have big construction projects. Each major construction project includes several complex tasks. Each of these tasks is a project in itself and it has its own schedule. The goal is to bring together all…
-
% Complete staying 0
Good Afternoon, I am new to Smartsheet, and am having trouble with what seems to be a simple task. The parent % complete will not change from 0%, no matter what I put in the child's information. Thanks.
-
Report Gantt Chart Project Settings
I am trying to change the Gantt Chart Timeline Display in a report. The report currently has the standard display as follows: I am trying to get it to look like how I have it in the original sheet below: Whenever I try and click on project settings either nothing happens or I get the error message below: I submitted a help…
-
Filtering for critical path to a milestone
Hi everyone, I have a project that spans multiple years and contains many workflows. I would like to be able to track the critical path to different milestones (not just the last task in the sheet). Are there any tricks to doing this in smartsheet?
-
Make start date the same as predecessors end date
I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date? Thanks!
-
One off Saturdays in Gantt
Hi all, I work in construction and use the gantt chart heavily to manage scheduling subs. I have a unique situation for my project where I may have to schedule work on a Saturday. Is there any way to allow a single Saturday, instead of opening Saturdays for the duration of project?