Hello, first of all sorry for my English, I'm doing a translation from French. I work in the construction industry and we have big construction projects. Each major construction project includes several complex tasks. Each of these tasks is a project in itself and it has its own schedule. The goal is to bring together all…
Good Afternoon, I am new to Smartsheet, and am having trouble with what seems to be a simple task. The parent % complete will not change from 0%, no matter what I put in the child's information. Thanks.
I am trying to change the Gantt Chart Timeline Display in a report. The report currently has the standard display as follows: I am trying to get it to look like how I have it in the original sheet below: Whenever I try and click on project settings either nothing happens or I get the error message below: I submitted a help…
Hi everyone, I have a project that spans multiple years and contains many workflows. I would like to be able to track the critical path to different milestones (not just the last task in the sheet). Are there any tricks to doing this in smartsheet?
I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date? Thanks!
Hi all, I work in construction and use the gantt chart heavily to manage scheduling subs. I have a unique situation for my project where I may have to schedule work on a Saturday. Is there any way to allow a single Saturday, instead of opening Saturdays for the duration of project?
Hi, all. I have data in table where two date columns are derived from formulas. When I try to use the Gantt chart functionality it says that my grid needs at least two dates columns and doesn't allow me to continue. I have two date columns but they are derived from formulas. Does the Gantt chart functionality not recognize…
I am trying to get data for a sheet which is repesented in the Gantt View. Since the ganttview already shows all the milestones and tasks that are under the milestones, getting that data would reduce our calculation by a huge chunk. any idea how can I do this via the api? The get sheets endpoint has include=ganttConfig but…
I am working on charting out dev tasks and need to display what our expected total monthly cost would be based on the tasks finished each month. I am struggling to find out a good way to have this either permanently displayed or easily accessible. I have tried reports but that only displays all of the costs and does not…
I'm expecting my next project to be subject to a lot of external influences and dependencies. When faced with this challenge I like to show the original plan and the actual / newly forecast start and end dates to report upwards effectively and discuss the any slip. So in effect each activity has an "originally planned"…