-
Annotation
Often when doing a delay analysis or some other schedule work, we need to annotate the Gantt chart to highlight certain areas, add notes etc to give the data more impact. Currently this has to be done in another program like PDF, can Smartsheet make such an option available?
-
Vertical line in Gantt - Data Date
It would be great if there was a way to add a drop line on the Gantt view i.e a vertical line that communicates important information like the data date i.e the date the schedule was updated These visual tools are important for consultants when trying to communicate data to clients etc
-
Visually demonstrate delay
When doing presentations its critical to be able to visually communicate delay. Currently in Smartsheet we can turn on the baseline to see planned vs actual however it is very limited i.e no ability to change the colour of the baseline, show durations of delay with an arrow etc. To be able to compare activities from one…
-
Ability to allow all users to set the "open to today's date" Gantt view option
This option should not be restricted to Administrators, but should be able to be chosen for all users, or at least Editors. Thanks Simon
-
Gantt View: Open to Today's Date Option
I am a fairly new SS user and am owner/admin for a large project/Gantt sheet that is shared internally with other Project Managers, who are also fairly new to SS. They have edit permission, but are not admins. I have set the project option to open the sheet/Gantt view to 'today's date'. My Gantt view opens as…
-
Control resoultion for export Gantt to image
The current export Gantt to image tool is useless because the resolution is so low that text is unreadable. Please either up the image resolution, or (preferably) provide us with a slider to adjust the image resolution setting. Thanks.
-
Finish Date Static vs Duration Static
Can the Finish date be static and have the start date and duration dynamic? Example: I have Task 1 and Task 2. Task 1 has a duration of 5 days and Task 2 has a duration of 10 days. Task 2 has a dependency on Task 1. But Task 2 has a due date that cannot change. If Task 1 goes over the 5 days by one day, I update the…
-
Multiple Date Ranges within the Same Row
From what I read this is still not an option with Smartsheet. I would also like to have multiple date ranges within the same row. I would like to be able to look at a project (start to finish) but also like to see Section A, Section B, and Section C date ranges within that project on the same gantt chart row. I currently…
-
Gantt chart finish date change and synced sub task changes
Hello, I am new to Smartsheet and am trying to figure out if it's possible to do the following in a Gantt Chart/Critical Path: Is it possible to have all subtask dates in a gantt chart update if the finish date has to change? For instance if the finish date is delayed and there is now more time to complete tasks/subtasks,…
-
Gantt View on Dashboard not starting at today's date
Hello! I have a report that summarizes deliverables from several sheets, with the information displayed in a Gantt view. On the Gantt Timescale Settings, the checkbox to open the view to today's date is checked. I created a dashboard and have the report on it with the Report Widget. When I load the dashboard, it properly…