Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
'Conditional'/Multiple Predecessors
Is it possible for start date of a task to be based on dates tied to one of two other tasks?
E.g. Task 2 must start not more that 10 days from completion of Task 1. Under normal circumstances, this allows task 2 to start not more than 10 days from start date of task 3. If start date of task 3 must be accelerated, however, can start date of task 2 be not less than 10 days from start date of task 3?
Or:
If time between Task 1 and Task 3 > 20 days, Start Date of Task 2 = Task 1+ 10 Days
If time between Task 1 and Task 3 < 20 Days, Start Date of Task 2 = Task 3 - 10 Days
Thanks all.
Mike Morgan
Comments
-
Hello Mike,
It looks like you're wanting something similar to constraints in MS Project.
We currently don't have that functionality in Smartsheet, but when you have a chance, please submit your feedback to our Product team directly using the Product Enhancement Request form under Quick links on the right of the community site.
What you can do is add lag or lead time to your tasks to delay their start time. More on lag and lead time can be found in our help article here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives