-
Merged: Develop the ability to add CONSTRAINT TYPES to project schedules
This discussion has been merged.
-
How to print selected columns
I'm new to Smartsheet and I have inherited some sheets from my predecessor. I'd like to print a Gantt chart and a grid. My question is, how do I specify which columns will be printed? When I print the grid it prints all columns I can see on the screen but I want to exclude some. When I print the Gantt chart it only prints…
-
How can Smartsheet be utilized to create a searchable resource repository?
Hi everyone, My team and I are exploring a Smartsheet solution for a searchable resource repository. We currently have a variety of resources available to our managers to help them coach their associates, including job aids, videos, simulations, etc. These resources are housed in different locations. We would like to…
-
Backward timeline?
Hello! I'm looking for help to create a simple sheet that starts with a launch date, and assigns tasks dates using task durations. I'd like to use columns like tasks, start date, end date, duration and predecessors. Is there an extra column with a formula that will be needed?
-
How to calculate parent-level values in multiple columns (not just % Completed)?
Hi, In my project sheet, only the % Completed column rolls up automatically using parent/child logic. That works fine. But I want to do something similar in other columns, like: Variance from Baseline (%) Weighted Variance Planned Progress (%) These are all calculated row by row, but I want to show an accurate value at the…
-
Customizable view options in Smartsheet Card View
I think it would be useful to be able to customize the Card view in Smartsheet grids and reports to include additional view options, such as by date or other custom columns, instead of being limited to the default options like "status", "schedule health", or only being able to view by columns that are dropdowns or symbols.…
-
Different way to track health
I have a project without a set end date and am being monitored on if I am getting it closer to completion by the % complete field, how can I make a formula that tracks health based on that forward progression so that if my % complete goes up it stays green but if it stays the same for three days it goes to yellow and if it…
-
Merged: Outlook Add-In
This discussion has been merged.
-
Best Way to Facilitate Task Hand-Off to Different Assignees
I've been trying to build out a solid "template" of sorts to help manage numerous tasks/subtasks for similar but different projects. Each row contains a parent task or a child task (subtask). Many of these tasks change hands throughout the process of the project as it evolves toward completion. As one example, Assignee A…
-
PMO Template-- Archiving Projects
I have begun setting up/ using the PMO template. I am wondering if there is a way to archive old, completed projects so my project-level folder stays organized but the data is still available. Thanks