Hello there, this is my first discussion and I have a feeling this might not be possible, hehe. I would like the Status (a dropdown list column) to change to a certain value ("Complete") if the Date (…
Hi, I am new to Smartsheet, and I have been using it this last month to manage one of my projects. One of the area I wish there was some improvements and changes, would be the Update Request area: 1. …
What we want, is to be able to generate a daily or weekly report of how much time each person worked, and on which tasks. We need to be able to not only see the efficiency of the tasks, but also of th…
Hi Folks. I see that there have been discussions for years about a feature that still seems to be missing. Even if now the duration of an event can be determined pretty detailed, we still can't tell t…
We need to overcommunicate and manage our offshore teams better. What are best practices in terms of tracking and managing ALL the schedule and tasks using Smartsheet? One master schedule containing t…
We have a smartsheet with multiple rows of activities and column headers: "PSA Start" and "PSA End" dates. We want to build 3 reports that shows: (1) PSA End dates due in 0-2 weeks (2) PSA End dates d…
We are using the Baseline "workaround" by creating the Actual Start, Actual Finish and variance column formulas. What method has worked for you to compare the baseline to the actual since it's not sup…
I'm new to Smartsheet and struggling with a few things, one in particular is wearing me out. I have several rows of linked cells that pull number values from another Sheet. I'm trying to Sum total the…
There are two elements to Lags and leads that I believe are greatly needed in Smartsheet Projects: 1 - Being able to use elapsed time in Predecessors i.e. +e6h for Paint drying time or +e5d for waitin…