Is there an easy way to reverse a timeline that was originally based off of a start date, but should be based on the end date? We plan a lot of meetings where the meeting dates are always moving and w…
I have a report that's running every day against a single parent row to grab totals. A few cells of that one, single, lonely row. I'm looking for a way to automatically copy the report's information i…
Hi there I will like to know ...is there a way where the end date column marks by his own every time i mark the complete check box on rorws. I will like to know is there a way to do that. thanks
While building out a Gantt or waterfall chart in Smartsheet, it is not uncommon to have some tasks that can only occur during a weekday while others can occur on weekends. It would be great if one cou…
I've been working in a CPM schedule. The original showed a 141 day duration, starting 12/12 and ending 05/04. I'm updating some of the relationships as I had to rearrange the work pattern a bit, now m…
Hi all, I have a couple questions for all the Smartsheet pros out there! I'm working on a sheet and I would like my team members to be able to update its content. The first problem is that I would lik…
hi, i see some potential of lose of my data if shared to others. for example, my project schedule shared to partnes and they have to update the status, since they are editor and they can delete my row…
I've been playing around with report builder, to create a summary page of all my sheets. I have a check box I use to filter the lines I want on the report, which are typically the first/top line, whic…
I am in the process of developing some work flow sheets for my team and I would like them to do the bulk of their submissions via web forms. Is there a way to create dynamic hierarchy whereby when a f…