Different Settings in Same Project Sheet
Is it possible, by formula or settings to have within the same project sheet, some tasks & sub-tasks that will need to use a 7-day work week (no weekends, no holidays) and also some tasks (and sub tasks) that will need to utilize the 5-day work week and holidays? To clarify, all of this is in the same sheet for a single project. This is to create a working schedule for a team to follow. No dashboard.
Any ideas to accomplish this are welcome.
Best Answer
-
Yes! If you're using a Project Sheet with specific working days and times enabled (e.g. 5 day work week and holidays), then on the specific rows where you want it to be a 7 day work week you can use elapsed time by adding an e in front of the duration.
Here's more information: Work with Duration and Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Yes! If you're using a Project Sheet with specific working days and times enabled (e.g. 5 day work week and holidays), then on the specific rows where you want it to be a 7 day work week you can use elapsed time by adding an e in front of the duration.
Here's more information: Work with Duration and Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
@Genevieve P. any time I see a response from you, I know it will be amazing!
Thank you for your answer and the extra information, both were extremely helpful!
Andrea
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives