How to capture Actual Finish Time for a Cutover Task
I have created a cutover Plan in Smartsheet and all tasks in the plan has these columns : Task, Duration, start Date and Start time, End Date and End time, Actual Start and Actual Time, Actual Finish Date and Actual Finish time.
I am able to calculate start and end dates based on duration but I’m only able to capture Actual start and Actual Finish dates based on workflow responses once the task gets triggered and submitted by the user as 100% done.
What is the way or formula to capture actual actual Finish time? Actual dates are captured using formulas but not actual end times
I want to use the Planned end time with actual end time to calculate variance and Reforcast the cutover plan end dates.
Answers
-
Hi @Devraj
I hope you're well and safe!
This might help!
Please have a look at my post below with a method I developed.
More info:
Would that work/help?
I hope that helps!
Be safe, and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!