Calendarweeks in Gantt Chart
Hi Everyone!
Is there a way to show calendar weeks in the header of a Gantt Chart?
I have set the timeline to "month" as a primary header and "week" as a secondary. But instead of showing "Jun 30" for the Sunday of week 29, I would like it to show "week 26" or "cw 26" or just "26".
Is that possible?
Thanks
Thomas
Answers
-
Hi,
You can change it in the Gantt Chart Setting table:
and then on tab: Gantt Timescale Settings:
Best,
Beata
-
Great. Thank you!
Is there a way I can also show calendar weeks in the date column of my task list?
The daily view is fine but it would be great if I could see calendar weeks somewhere, like it is shown in MS Outlook for instance, see below.
-
I hope you're well and safe!
Unfortunately, it's not possible now, but it's an excellent idea!
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 460 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives