Hi all! I have a question about control center. I want to make a global update but it's not possible in a predecessors column.
Context:
~1200 projects already provisioned
~500 have data related to the predecessors we don't want to lose
So I THINK I can remove the predecessors from the blueprint sheet itself and then "update reporting" but I don't know if I will hurt myself.
So, does this work?
If so will I lose my data?