Automation Errors - Not going to Correct Approver

Hi everyone,

I'm encountering a problem with my workflow automation for system change requests. I have three separate workflows, each corresponding to a different set of manager and director approvals.

Expected Behavior:

  • Country X: Manager 1 -> Director 1
  • Country Y: Manager 2 -> Director 2
  • Country Z: Manager 3 -> Director 2

Actual Behavior:

  • Country X: Manager 1 -> Director 2
  • Country Y: Manager 2 -> Director 1

Country Z is functioning as expected.

Troubleshooting Steps:

  • Rebuilt the workflows multiple times
  • Changed email addresses several times

Additional Information:

  • Automation restrictions are not in place.

Any suggestions or insights would be greatly appreciated.

Best Answer

  • kowal
    kowal Overachievers Alumni
    Answer ✓

    Hi James,

    It's not very typical behaviour of Smartsheet workflows. As those are 100% accurate.

    It's difficult for me based on your problem description to figure out what can be the issue.

    but….

    Instead of having 3 different workflows have you considered having only one? and for each director to have different condition? You can have many Paths of conditions to be met before sending to Director 1, 2 or 3 …all in one workflow.

    I think it will be much easier to manage and see errors as well.

    Tomasz Kowalski

    The Real Smartsheet Enthusiast

    Is there anything else we can help you with? - book your time!

    MASA Consult - Your Aligned Smartsheet Partner

    Find us on LinkedIn!

Answers

  • kowal
    kowal Overachievers Alumni
    Answer ✓

    Hi James,

    It's not very typical behaviour of Smartsheet workflows. As those are 100% accurate.

    It's difficult for me based on your problem description to figure out what can be the issue.

    but….

    Instead of having 3 different workflows have you considered having only one? and for each director to have different condition? You can have many Paths of conditions to be met before sending to Director 1, 2 or 3 …all in one workflow.

    I think it will be much easier to manage and see errors as well.

    Tomasz Kowalski

    The Real Smartsheet Enthusiast

    Is there anything else we can help you with? - book your time!

    MASA Consult - Your Aligned Smartsheet Partner

    Find us on LinkedIn!

  • Thanks Tomasz, I did think that having the 3 may be an issue as almost they are tripping over each other and could confuse it. At the time it seemed easier to visualize the separation at the time, but I might have taken a shortcut there.

    Let me try it out and see !

    Thanks for the prompt reply !

  • @kowal Looks like it worked! There were a few changes to the status columns, but it seems to be working as intended. Thanks for the final push I needed to get this automation reconciled.

  • kowal
    kowal Overachievers Alumni

    Happy to help!

    Tomasz Kowalski

    The Real Smartsheet Enthusiast

    Is there anything else we can help you with? - book your time!

    MASA Consult - Your Aligned Smartsheet Partner

    Find us on LinkedIn!