Outlook App and Date Column Error

Options
Emily Swartz
Emily Swartz ✭✭✭
edited 06/14/22 in Add Ons and Integrations

I am using the Outlook app for Smartsheet (which I love!) but when entering info from Outlook, I am unable to edit a date column if there are more than one in the sheet.

Ex. If I have a Start Date and Finish Date for a project, I can only edit the Start Date column from Outlook. The Finish Date field is grayed out.

Is there a way to correct this issue?

Comments

  • Shaine Greenwood
    Options

    Hello,

    Finish date columns currently can't be edited from the outlook app, as they drive dependencies in your sheet. You should be able to edit the Start date and duration, which will then change the finish date for you.