Automatically marking something as complete when requirements are filled

sync
sync ✭✭
edited 12/09/19 in Formulas and Functions

Hello,

I was wondering if someone would be able to help me with a problem that I have been struggling with. I would like to make it so that when a checkbox is checked, in another column, called status, that it would switch and say complete. The status column is a Dropbox, containing Completed, In-progress and Not started. Is this possible? Also I don't want to lock the column as it would need to switch between In-progress and not started, however instead of manually having to switch to completed it does it automatically once the checkbox is checked.

 

Kind regards.

Comments

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!