How many cascading multiple sheet dependency can smartsheet can do?

Dynamics
Dynamics
edited 12/09/19 in Smartsheet Basics

HI,

 

Its me again doing cascading dependency on different sheets.

I tried 2 cascading project sheet dependency and it works.

I try doing 3 tomorrow but a question lingers:

How many cascading multiple sheet dependency can smartsheet can do without any issue?

 

Thanks

D Micu

Comments

  • Hi D Micu,

    There isn't a hard limit on this. Performance in Smartsheet depends on a few factors:

    • High use of advanced functionality such as dependencies, cell links, and formulas. We typically see degraded performance when people add a lot of formulas to a sheet or use large formulas.
    • Browser extension or outdated browsers can reduce performance. Try disabling extensions and updating your browser to troubleshoot if you get slow load times.
    • Network blocking or slow networks make it more difficult for your computer to connect with Smartsheet and you can see performance issues. Try a different network to troubleshoot this and work with your IT team long term to improve connection to Smartsheet.