Gantt Chart Start & Finsh dates Change

Quentin_H
Quentin_H
edited 12/09/19 in Smartsheet Basics

If my Start or Finsh date changes from the orginal schedule how can we show the progress or delay in the schedule.  Currently I'm re-entering the Start or Finish date.  So I'm lossing the orginal to show us any gains or losses.  I do not want to loss the predecessors link to the task.