I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…