I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
Hi everyone, in several of my Details Views for multiple Dynamic Views, text fields and/or checkboxes that are configured in the Dynamic View settings are not appearing in the Detailed View. Is anyone else seeing this today? I've not updated any of my configurations lately and don't know how to explain this! Thanks!
Can someone tell me how to get rid of the 120.0% max on this graph? It is always going total 100% and never any more, so I would like to use more of the space for graph display purposes. I even tried reducing it so that the largest value was 99.999%, thinking maybe being exactly 100 would cause the next "level" to…
I have 2 sheets that I need to link: Sheet 1 - collects user registration information through a form. Sheet 2 - I want to link some columns to copy partial data collected in sheet 1 and have it show in sheet 2. I don't want to copy the entire row, just select columns and I don't have Smartsheet Bridge. Each sheet has a…