How to track external dependencies
I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
Comments
-
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives