I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
I have imported a fillable PDF form and have moved over all of the corresponding tabs. When I hit save to generate the form it get the following: To generate documents, please add some content to your sheet. Any ideas?
Hello, Our Task Tracker sheet is used to manage and collaborate on internal tasks. Each team member received a daily email containing all tasks assigned to them, and we all LOVE the update request feature where we use a webpage that resembles a form to review & update each request, click next, go through all tasks, and…
This is what I would like to accomplish using Smartsheets but I am struggling to find the best way to go about it. Each year we get new vegetable varieties that we need to test in various locations at different times. I would like a tool that I can follow each variety up with a grower. The following data is added:…