How can I get the =WEEKNUMBER consider a week from Monday to Sunday. I have some entries on Sundays that is showing week number of following week.
Weird - Do you have an example date where this is happening?
From the notes:
Hi,
I am actually coming across the same issue and need the weeknumber to calculate Sunday to Saturday. Is there any way that the formula can be adjusted for this?
Thank you,
Crystal
Here is what I came up with, if this is still relevant to you.
=IF(WEEKDAY([Work Day]@row) = 1, WEEKNUMBER([Work Day]@row) + 1, WEEKNUMBER([Work Day]@row))
where Work Day is when the employe worked. So I tricked the system in adding 1 to the weeknumber when the day number is 1 (so this Sunday end up next week) making it a week from Sat to Sun.
How can you get rid of the uncategorized land in a report timeline view?
Please help! I understand that we can't customize the gantt chart bars anymore if it is a parent row but why am I getting random colors on the bar view in my report? I would prefer it remain grey. The first picture is the Smartsheet and the second one is the report pulling from the sheet.
Trying to understand why we don't have the option to remove a status by automation. For example, when external customer approves a proof, it fills in "APPROVED BY CUSTOMER" which then triggers automation, but the existing status of "SENT TO CUSTOMER FOR APPROVAL" remains as I cannot set automation to do that.