I have checked all of my settings in the main sheet and dependencies are not turned on nor predecessors, the box remains grey? I also have ensured that in the details panel, it is not read only.
By any chance is the finish date calculated by durations based on a start date or by a formula? I don't have the dynamic view, but in reports when a field is calculated with formulas it is uneditable.
Mike is correct. Also, make sure the date column is not locked in the main sheet.
If the finish date is assigned in the dependencies settings in the Gantt View then you will not be able to change it. I think that is the case even if the dependencies check box is not checked.
Hi Marc,
Is it the same for all rows? Are you using any Field Logic rules?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Thanks This was driving me crazy!! once I Changed the date to another date column in dependencies (although not active) it worked.
I have set up DataShuttle in Smartsheet to automatically offload files and replace existing versions in Google Drive . Unfortunately, the replacement feature is not working as expected, and the files are not being overwritten properly. Can you please support to get this fixed?
Hi all, I'm trying to automatically update a Smartsheet dashboard widget using data from Tableau. Currently I am manually refreshing or updating the widget, and I'd like to find a way to automate this process. Specifically, I'm wondering: Is there a native integration that allows a Tableau view or chart to live-embed in a…
If user A owns a data shuttle and set it up to save the csv in an offload workflow to that individuals google drive and then user A goes on vacation and user B now is responsible for running the manual shuttle. When user B ran the shuttle, it created a NEW csv offload file. Is that because of the setting having to do with…