I have checked all of my settings in the main sheet and dependencies are not turned on nor predecessors, the box remains grey? I also have ensured that in the details panel, it is not read only.
By any chance is the finish date calculated by durations based on a start date or by a formula? I don't have the dynamic view, but in reports when a field is calculated with formulas it is uneditable.
Mike is correct. Also, make sure the date column is not locked in the main sheet.
If the finish date is assigned in the dependencies settings in the Gantt View then you will not be able to change it. I think that is the case even if the dependencies check box is not checked.
Hi Marc,
Is it the same for all rows? Are you using any Field Logic rules?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Thanks This was driving me crazy!! once I Changed the date to another date column in dependencies (although not active) it worked.
I ran into an issue when creating a new workflow in Bridge and got the following error: "You have reached the maximum number of repeated schedules for workflows in your account. You must reduce the number currently used to be able to create new schedules." This took me by surprise since I couldn’t find these limits…
Hello everybody, Does anybody use Sproof in combination with smartsheet instead of DocuSign? Is there any possibility to connect smartsheet to sproof? Thank you in advance!
Hi everyone, I’d love to get some insights into how others in the community are handling e-signatures within their Smartsheet workflows. Naturally, DocuSign seems like the obvious choice since it integrates directly with Smartsheet. What has your experience been with it so far? I’m also curious about alternative tools—has…