Automating the Correct Start and End Date within Control Center Project
When creating a project in Control Center, when the project is spun up and moved from our Intake Form/Sheet to Project Generation (On the Active project Sheet).
The Control Center system is automatically putting in a random date every time a project is created. These dates are put in on every project we create. I went through the blueprint settings and was not able to find anything in the set up that had start and end date.
Is this something we can change so the System would just put in "Today's Date" when the project was created, or leave it Blank? It is affecting some KPIs we have for overdue tasks etc..
Here is an example of where it is automatically importing the incorrect dates into the control center project plan.
Has anyone seen this before and know of a fix or solution? Thanks in advance for the support and information!
Answers
-
Hello @bradleyesmith86431,
I would recommend looking at the Start Date and End Date fields in the blueprint's "Profile and Data Selection" and the project's "Profile Data". If needed, more information on this can be found in our help article: https://help.smartsheet.com/articles/2478431-scc-define-track-project-with-profile-data
-
That was it! I was able to get access to the Project Blueprint and change it!
Thanks.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives