One person has multiple jobs on one day

Hi,

I'm looking to adjust my sheet based on one person having multiple jobs in one day. What I'd like to do it have it be that each person has only one job per day. Ideally, SS would be able to look at all other jobs this person is assigned to and adjust the start dates of other jobs based on available slack time (away from critical path). For example, if I have Aaron assigned to do job A and B on the same day but B is not on the critical path, SS would push off start time by one day. Is there a way to do this?

Answers