Automatically update related tasks when one date changes
Hi!
My team is using Smartsheet for project management, and I want to know how to update due dates for tasks that are related. For example, if my original due date is 1/1/17, and there are several other tasks that are related to the starting date (edit, layout, print, etc.), if I change the date of one of those tasks, how can it automatically update the others to reflect this change? Let's say I need to change the layout date from 1/1/17 to 1/5/17, but the print date is set to 1/5/17. Obviously my print date would need to be adjusted to reflect the delay in layout. Is that possible?
Thank you!
Sarah
Comments
-
Sarah,
You'll likely want to take a look at predecessors:
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Hope that helps.
Craig
-
Hi Craig,
Thank you for the help! I think predecessors should work perfect for us once we get the hang of it!
Sarah
-
If you aren't familar with them from another PM tool, the version in Smartsheet should be able to handle your use-cases. Just post any questions on the Community. Some very experienced people that can help. I can too.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives