View dependencies
Hi everyone,
one question regarding predecessors. Is there option to quickly see which tasks depend on "Task1". In this case with 6 tasks is easy since I can take a look at predecessors in another nones, but when we have project with couple thousand rows I can´t go in search tasks by task to find dependencies. Ive tried to navigate trough gant chart but its also hard to do it
Answers
-
Hi Davor Dumeljic,
You can use filter option to see tasks that depend on a particular task as shown below
Hope it helps.