View dependencies
Hi everyone,
one question regarding predecessors. Is there option to quickly see which tasks depend on "Task1". In this case with 6 tasks is easy since I can take a look at predecessors in another nones, but when we have project with couple thousand rows I can´t go in search tasks by task to find dependencies. Ive tried to navigate trough gant chart but its also hard to do it
Answers
-
Hi Davor Dumeljic,
You can use filter option to see tasks that depend on a particular task as shown below
Hope it helps.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives