I have two sheets that have linked cells. I want to use the workflow to make the tasks from the second sheet disappear if the Status column says complete. Is this possible? I know how to set up a workflow to move cells to a new sheets but it does not seem to be working. Is this because I have the cells linked to another sheet? Please let me know
Answers
-
Hi @Sara Moore
Hope you are fine,To prevent infinite approval loops, cells which contain cross-sheet formulas or cell links will not trigger an automation which automatically changes the sheet (Move Row, Copy Row, Lock Row, Unlock Row, Approval Request). To work around this, consider using time-based automation or recurrence workflows.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Follow up question. If you copy a row to another sheet will it still update along with the parent row on the source sheet? That is why i currently have them linked I need one sheet to update other sheets but only want to physically update the one.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives