Dear community,
I have created a sheet for Data Center migration planning. By definition these activities are planned during normal working days (Mon-Fri) but the migrations happen during weekends, as it requires to stop servers and so that's the lowest impact to services.
This sheet has defined all days as working days to be able to use Sat and Sun as working dates.
I would like to link the cells of this sheet to another sheet (Target) that contains also links to other sheets.
Because the target has defined the working days as Mon-Fri, when I link the cells the End date is calculate to a wrong date (because it takes the start + duration from a sheet that is defined into 7 working days instead of 5).
What do you suggest to solve this issue?
- I cannot change the working days defined per sheet
- I tried but couldn't cell link only Start and End dates, without duration.
Thanks in advance,
Daniel