Project Schedule Baseline - Is History Kept when Re-baselined?

We are using the Project Schedule Baseline functionality, but recently learned that the Schedule can be Reset or Removed. Is there anyway to track how many times a Schedule has been 'Reset' or 'Removed' and baselined again? Our concern is that without the history being tracked on how many times it's been reset, we won't truly know the original intended scheduled dates. And the PM can continuously reset the baseline if their project goes off-track, hence looking like their projects are always 'on time'. Is that original data from the 1st baseline saved anywhere, or in any Metadata report? Thanks!

Best Answers

Answers